e-agenda.NET
Special Meeting re Operations
Agenda Item #5


Title
PM2 Wellington High School Auditorium Project Modifications

Description

This project modification contains the following item:

  • Additional Architectural Services in the amount of $3,500.00
  • Description:  Provide additional sidewalk (700' x 6') on the site to provide safe entry to campus from Greenview Shores to East side of Auditorium.
  • Cause:  School District Requested.
  • Justification:  A safe route needs to be provided into the campus for walkers coming from the south on Greenview Shores Blvd. by  installing a sidewalk along the main entrance
  • The Estimated Construction Cost is $19,000.00


Recommendation

I recommend the School Board approve Project Modifications in the amount of $3,500.00 to MPA Architects for Wellington High School, Auditorium Project #2191-8272, and authorize the Chairman and Superintendent to execute all related contract documents.



My Contact
Joseph M. Moore (moore@palmbeach.k12.fl.us)
Joseph M. Sanches


Financial Impact

The financial impact to the Project's Budget is $3,500.00.

The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.




Attachment:  Wellington HS Budget History.pdf
Attachment:  Wellington HS Capacity Utilization Table.pdf
Attachment:  Wellington HS Site Plan.pdf
Attachment:  Wellington HS Facility Space Summary.pdf
Attachment:  Wellington HS Data Panel.pdf