School Board Meeting 11-20-12
Agenda Item #55


Title
CP-2 North Palm Beach Elementary School Modernization Construction Management at Risk First Amendment

Description

Construction Management @ Risk Services required for the Phase I Guaranteed Maximum Price (GMP) with James B. Pirtle Construction Company d/b/a Pirtle Construction Company.  Phase I services consist of Demolition and Site Clearing.  All existing buildings will be demolished with the exception of Buildings #8 and #9.  Buildings #8 and #9 are existing 1-story classroom buildings.  These two buildings will be remodeled to accommodate the educational program and will be incorporated into the overall school design.  The demolition scope will also include removal of all existing underground utilities (water, sanitary, storm, electric, systems, etc.), as well as removal and/or on-site relocation of existing trees.

The completed Project shall be constructed to achieve Leadership in Energy and Environmental Design (LEED) Silver Certification, all requirements set forth in the permitted Construction Documents, Educational Specifications, Florida Building Code, Florida Accessibility Codes, District Master Specifications, Design Criteria and all other applicable specifications.  Construction shall be in accordance with the Educational Specifications approved by the Board on January 18, 2012. 

Approved Budget for Construction:  $21,409,000.00

Construction Type:  Tilt-up 

No. of Stories:  Two Story

 

Gross Square Feet:  89,420

Budgeted Construction Cost per Gross Square Foot:       $239.42 

 

Total New Student Stations:  753 

Budgeted Construction Cost per Student Station:         $28,432.00 

 

Preconstruction Phase Services Fee:                          $166,825.00

Reimbursable Costs:                                                 $41,000.00 (not to exceed)

Phase I GMP: (Demolition)                                        $699,452.00 

 

Total:                                                                        $907,277.00

Small Business Enterprise (SBE) Participation: School Board Policy 6.143 allows for SBE Participation goals and that firms awarded work on such projects fully participate in the SBE program.  The Contract as a result of this RFP establishes SBE goals. 

Pre-construction

Certified SBE CM Sub-consultant Participation: 30%

Certified SBE CM Sub-contractor Participation: 30%

 

Phase I GMP

Certified SBE CM Sub-consultant Participation: 30.38%

Certified SBE CM Sub-contractor Participation: 48.47%



Recommendation
I recommend the School Board approve the First Amendment to the Construction Management at Risk Agreement to establish the Phase I Guaranteed Maximum Price (GMP) in the amount of $699,452.00 with James B. Pirtle Construction Company, Inc. d/b/a Pirtle Construction Company and authorize the Superintendent and Board Chairman to finalize and sign all required documents for the Phase I GMP for North Palm Beach Elementary School Modernization, Project No: 0131-7503.

My Contact

Michael J. Burke (mike.burke@palmbeachschools.org)

Joseph M. Sanches (joseph.sanches@palmbeachschools.org)



Financial Impact
The financial impact is a committment of $699,452.00.  The source of funds is the corresponding Capital Projects Budget.


Attachment:  CM@RISK RFP NORTH PALM BEACH ES MODERNIZATION with Addenda.pdf
Attachment:  North Palm Beach ES DATA PANEL.pdf
Attachment:  NPB ES CSA Tables-September 2012.pdf
Attachment:  PPE-PIRTLE CONSTRUCTION.pdf
Attachment:  EXH B NPB FACILITY SUMMARY from Approved ED SPECS 0131-7503-2.pdf
Attachment:  EXH A NPB Approved ED SPECS 0131-7503.pdf
Attachment:  Beneficial Interest-James B. Pirtle Construction dba Pirtle Construction Company.pdf
Attachment:  First Amendment-NPBES-James B. Pirtle Construction.pdf
Attachment:  NPBES PH I GMP.pdf
Attachment:  Legal Checklist-NPBES-James B. Pirtle Construction.pdf