School Board Meeting 04-17-13 at 5pm
Agenda Item #51


Title
CP-5 North Palm Beach Elementary School Modernization Construction Management at Risk Second Amendment

Description

Construction Management @ Risk Services required for the Phase II Guaranteed Maximum Price(GMP) with James B. Pirtle Construction Company d/b/a Pirtle Construction Company. The scope of work includes vibro-compaction of the soil within the new building footprint, chemical grouting under Building #8 and #9 (existing to remain), and the new building pad.

Approved Budget for Construction: $21,409,000.00
Construction Type: Tilt-up
No. of Stories: Two Story
Gross Square Feet: 89,420

Budgeted Construction Cost per Gross Square Foot: $  239.42
Total New Student Stations: 753
Budgeted Construction Cost per Student Station:  $  28,432.00

Preconstruction Phase Services Fee:                     $166,825.00
Reimbursable Costs:                  (not to exceed)        41,000.00

Phase I GMP: (Demolition)                                     699,452.00
Phase II GMP:                                                        382,820.00

Total:                                                                  $1,290,097.00

Small Business Enterprise (SBE) Participation:
School Board Policy 6.143 allows for SBE participation goals and that firms awarded work on such projects fully participate in the SBE program. The Contract as a result of this RFP establishes SBE goals.

The Phase 2 GMP proposal includes 30% SBE participation for the CM Partner (Asset Builders) but no SBE participation for the sub-trades due to the limited scope of work and associated bid results.  However, Pirtle is committed to meet the 30% SBE sub-trade participation goal when they submit their Phase 3 GMP proposal in the near future.  Their total contract value (Phases 1, 2 & 3) will be evaluated when reviewing the overall SBE participation of the sub-trades.

Pre-construction
Certified SBE CM Sub-consultant Participation: 30%
Certified SBE CM Sub-contractor Participation: 30%

Phase I GMP
Certified SBE CM Sub-consultant Participation: 30.38%
Certified SBE CM Sub-contractor Participation: 48.47%

Phase II GMP
Certified SBE CM Sub-consultant Participation:  30.32%
Certified SBE CM Sub-contractor Participation:  0%



Recommendation
I recommend the School Board approve the Second Amendment to the Construction Management at Risk Agreement with James B. Pirtle Construction Company, Inc. d/b/a Pirtle Construction Company in the amount of $382,820. for North Palm Beach Elementary School Modernization, Project No: 0131-7503, and authorize the Superintendent and Board Chairman to finalize and sign all required documents for the Phase II Guaranteed Maximum Price (GMP).  

My Contact
Michael J. Burke (mike.burke@palmbeachschools.org)
Kristin Garrison (kristin.garrison@palmbeachschools.org

Financial Impact
The financial impact is a commitment of $382,820. for the Phase II GMP. The source of funds is the corresponding Capital Projects Budget.


Attachment:  Checklist-NPBES-Pirtle Construction.pdf
Attachment:  Signoff -NPBES Phase 2 GMP.pdf
Attachment:  Second Amendment-NPBES-Pirtle Construction.pdf
Attachment:  Executed First Amendment.pdf
Attachment:  Executed Agreement-North Palm Beach-James B. Pirtle.pdf
Attachment:  CM@RISK RFP NORTH PALM BEACH ES MODERNIZATION with Addenda.pdf
Attachment:  CP5 NPBES Phase II GMP Rev 2.pdf
Attachment:  Beneficial Interest-Pirtle Construction North Palm Beach.pdf